Project

General

Profile

Actions

Task #1946

open

Task #2187: Receiving Process (Training Setup etc)

Task #2089: Session 1 - Part specifications

Task #1999: 内部結合テスト / Internal Join Testing

M3-1 P→S 仕入検収実績/PI507 Goods Receipt

Added by Hiroaki Sato 2 days ago. Updated 2 days ago.

Status:
10_In-Process
Priority:
10_Medium
Assignee:
-
Start date:
10/08/2025
Due date:
12/15/2026 (Due in about 8 months)
% Done:

100%

Estimated time:
(Total: 0:00 h)

Subtasks 1 (1 open0 closed)

Task #1848: インターフェースの実装検討 / Consideration of interface implementation10_In-Process10/08/202512/15/2026

Actions
Actions #1

Updated by Hiroaki Sato 2 days ago

  • Subtask #1848 added
Actions #2

Updated by Hiroaki Sato 2 days ago

  • Status changed from 00_Untouched to 10_In-Process
Actions